Budget Question2

I would like to prepare a budget based on Total or Sub Total Groups, eg Total Sales. This seems to be impossible because SAP only allows budgets against the lowest level (Level 5) Nominal Structure.

I need this since we have a lot of individual Nominals and it will take a long time to set each Nominal Budget, so I would like to enter a higher level Budget if possible or any other practical idea.

Thank you


PS The other practical reason I cannot set individual Budgets at level 5 is that we are using SAPb1 for the first year and no historical information is available apart from TOTAL Sales.

Not what you were looking for? View more on this topic or Ask a question