T-code: S_ALR_87013611 - Cost Centers : Actual/Plan/Variance

former_member267332
Participant
0 Kudos

hi,

Currently the above T-code provide data in USD. In order to get RMB, I have to further drill down the report.

Is there any T-code that I can display this report in RMB straight away?

The steps is as per below:

1. Enter T-code: S_ALR_87013611

2. Enter the controlling area, fiscal year, from period , to period and plan version. Finally enter the cost center group.

3.Click on Execute

4. The results displayed.

5. Double click on Act.costs

6. Select Area: Actual/Plan 2 currencies

7. This is the page that i needed.

Can i skip all the step and get the results in "Step 7" directly.

Kindly advice me.

Thanks.

Joo

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

S_ALR_87013611 is default standard report generated by SAP. Goto Transaction --> GRR2.

Select Report 1VK Where the program S_ALR_87013611 is 1SIP-001, and the area what you are selecting is 1SOT-001. Copy this program as ZSOT-001 and generate your a new report. Hope this will solve your purpose

Assign points if useful

Regards

Kaarthik.D