One Excise BOND For multiple plants

Former Member
0 Kudos

HI,

We have an Requirement like Physically only one plant , one excise registration and one excise bond , but logically we have multiple plants in sap deliveries will happen from all the plants , Excise bond creation as well as ARE1 Creation and Updating is happening for only one plant in SAP , but deliveries are happening from all the plants.

Please suggest me how we can handled this scenario

Thanks & Regards,

Gangi.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As understand from your query, If suppose company having plants A,B,C,D and in that only A plant is Excisable and other plants are non Excisable that is Bonded plant. In this case if you are dispatching any material from A then only system to reduce the value/quantity based on the Bond defined and also same for ARE1 but for other plants not required to create any Excise Invoice or ARE1 or dispatch against bond because these plants are non excisable. In your system settings maintain the plant settings as non excisable for A,B,C

Please correct if any thing i written wrong.

Regards