After doing TECO I did settlement of the WBS..Now when i try to UNDO the TECO ,it is not happening.It is not showing any error also.
Hi Sarin.
There are two possibilities I see first:
You have set status completed and cannot take back technically completed. In this case take back completed first.
You have a user status set that is preventing taking back technically completed. You best have a look into customizing transaction OK02 to see what the relevant staus does and if you can or have to redo the status.
Best regards.
Jens Schmid
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well. In this particular project, is there a user status set? Are any other stauses set? If it is one project only it might very well be the settings of the corresponding WBS element or of those below.
What are the statuses of that WBS element? Can you describe a little more detailed why you cannot redo the status?
What does error description tells?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.