project number is created by system

Former Member
0 Kudos

Hi,

you know ,when you creat a project ,you need input a string numner ,otherwise system will give a infomation "pls input project code" when you save.

Now ,I hope system provide a auto-way to save project ,not to input project code .system distribute number to new project.

Tks!

best!

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member201206
Active Contributor
0 Kudos

Hi Du Ming,

It should be possible to let the system generate the WBS ID, if you create a new one. I think, the responsible customizing is the 'Project Coding Mask', please check it out.

Project System -> Structures -> Operative Structures -> Work Breakdown Structure (WBS)

Kind regards,

Zhenbo

Former Member
0 Kudos

When you create the project, click on the pulldown for the project definition field. This will give you a window "Find Open Number". Provide a start value or finish value for the project definition. For example, if you have created a project coding mask for your projects as PS-XXXXXX, enter PS-00000 and click the "find" button at the botton to get the next open number. Select it and it will become your auto-generated project definition for the new project.

Please reward points if helpful.