cancel
Showing results for 
Search instead for 
Did you mean: 

Threshold Values - Project Structure

Former Member
0 Kudos

Dear All,

Iin my cProjects system, threshold value rules are not working in Project structure, where the symbols are showing properly in Evaluations. I have done the Extract Layout mapping to Project Type as well. But still i am not able to get the threshold values in Project Structure.

regards,

rajesh.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

If you want to test if it works press the button Check that appears in the Structure view.

It runs the evaluations defined for your project type

Neil

former_member201206
Active Contributor
0 Kudos

Hi Rajesh,

Would you please check, if the evaluation is triggered according the customizing. Or you can run it via report DPR_EVE_BATCH_DPO.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Rajesh,

Did you perform customizing for aggregation of threshold values in 'Project Type'?

Let me know if this helps.

Regards,

Vivek Pandey