Hi there,
I am using CJ9BS the standard tcode to copy versions and try trying to copy version 0 to monthly version (12 version to keep history of version 0). It copy the total cost but not allowing me to copy the detail planning to cost elements which is done in version 0.
How can I copy planning from version 0 to monthly version upto cost element level?
Thanks
In the selection screen click on Settings and try checking the indicator 'Copy Detailed Planning of Cost Elements'
Regards
Sreenivas