on 04-25-2008 1:56 PM
How do I change the status of WBS element from REL to CLSD manually in the transaction CJ02.
The top level WBS element is in REL state so whenever I create a new WBS it is automatically set to REL state.
Please tell me how do I change the status to CLSD manually as this field is disabled for editing.
Hello,
In CJ02. Select the WBS... Go to Edit tab->Status>Close.
Then save the project.
Hope this helps.
Hemant