on 04-25-2008 12:27 PM
What is MRP Type?
MRP type controls which mrp procedure can be used to plan a material and which mrp parameters can be entered when maintaining material master. you have to enter this mrp type on MRP 1 view of material master record.
ND - No planning
PD - Planning
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
MRP type - Key that determines whether and how the material is planned. You have the following options:
manual reorder point planning
automatic reorder point planning
forecast-based planning
material requirements planning with forecasts for unplanned consumption
master production scheduling (MPS)
Raghu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.