Hi Gurus,

I need your help,one of my client needs the following requriment.

1. He is having the two workcentre A and B

2. A has lesser tolarance and b has the higher tolarance

3.While confirmation the plan associated to the lesser or higher tolarance has to be automatically assign to the inspection lot.

I think in standard SAP, it canot be done

Kindly suggest me way out

Thanks in advance

Jai

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

If you have created two inspection plans for the same material with the same usage, at the time of GR syustem will prompt the user to select the inspection plan.

I do not think any configuration avaialble to meet your requirement.

Regards

YMREDDY

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jai,

1. You can go with the solution given by Mr. Reddy, You can cretate two insepction plans with two different tolerances assign the same material to both, system will give a prompt before releasing the lot for RR.

2. You create singal insepction plan, assign the Both materail to it then, in the charecteristics overview screen, select the Charecteristics that is having differnt tolerence, and then you can use the Dependant charecteristic.

Reward points is helpfull

Regards,.

Shyamal

Former Member
0 Kudos

Hi,

You are right probably there is no way out through standard customization.

But you can go for User Exit while doing GR.

Arpit