System proposed sched. lines on deferent date instead of material availabil

Former Member
0 Kudos

Why system proposed schedule lines on deferent date instead of material availability date.

I have created an order on 07.04.2008 we have given required delivery date on 31.03.2008 in schedule lines system proposed the delivery date on 10.04.2008

material has posted on 07.04.2008.

In Order Controls “Lead time in days” is -0, MRP views are not maintained for the material. It is “Scrap” material.

The material having 3 batches for the total quantity all the batches are posted on same date.

Item Material Quantity Batches Batch created Date

10 20080410 10 01 07.04.2008

20 20080410 20 02 07.04.2008

30 20080410 05 03 07.04.2008

Why system proposed schedule lines on 10.4.2008 instead of proposed on 07.04.2008.

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Why did you mention required delivery date as 31.03.2008 (i.e. why did you backdate) when order was created on 07.04.2008? Any reasons?

Since you have checked everything, why don't you check customer master record for this customer? Did you maintain any 'Goods receiving hours' in Unloading points Tab?

former_member184555
Active Contributor
0 Kudos

Hi

Also check the corresponding route for the Transit time.

Thanks,

Ravi

Former Member
0 Kudos

Dear Ravi,

There is no route schedule determination; route is not activated for the order type.

Regards,

Bhanu

Former Member
0 Kudos

The date you see on the schedule line screen is the delivery date: The date on which the goods reach the customer's door!

So even if the material is available in your factory on 07.04, and it takes 3 days for the goods to be picked, packed, loaded and for the journey to reach the customer's door, then the delivery date will be shown as 10.04.

To check if this is true, you should select the schedule line and select the big button at the bottom called 'Shipping'.

Former Member
0 Kudos

Dear sir

There is no picking, packing and transportation lead time maintained even I checked in shipping point also.

regards,

Bhanu

Former Member
0 Kudos

Hi,

You please check the Picking time, Packing time and tranportation lead time.. in shipping point. Scheduling depends up on these field values also.

So please check these values. It may help u

Regards

Sankar

former_member217082
Active Contributor
0 Kudos

Hi bhanu

check the pick pack time and loading time and material availability date time in shipping point

check in MMR the in house production time in days and RLT in days

check the lead time in days in VOV8 for the sales doc type

Check the factory calendar also.

Regards

srinath