Transfering several PR's from R3 to one SRM bid invitation

Former Member
0 Kudos

Good morning,

We are using Plan driven procurement and bidding with Extended classic

scenario (SRM 5.0).

Indicator IMG sourcing is

"Sourcing via automatic bid invitation for items without a source of

supply"

Is it possible to transfer several PR's from R3 to one SRM bid

invitation?

Thanks in advance.

Alexey

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Thanks, i think it is possible whis IMG sourcing indicator:

"Automatic grouping and creation of a bid invitation in the case of items without assigned source of supply"

If a source of supply is not assigned, the report Automatic Grouping of Requirements for POs and Bid Invitations automatically attempts to create a bid invitation from several requirement items. If is unable to do so, this is recorded in the error log of the report.