SIS & LIS settings activate!!!!(Urgent)

Former Member
0 Kudos

Hi,

I need to activate my LIS & SIS in PRD. as when the client runs the SIS reports in PRD he doesnt get any data.

But when he runs the same report in DEV he gets the data.

when he runs any SIS or LIS reports he gets the mess. as no data existes.

I have been told to activate the SIS in PRD.

What does this mean & where to do it.

Rgds

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can use OMO1 Transction to Activate/update the infostructures related to the SIS

Regards,

Pawan

Edited by: pavankumarc@intelligroup.com on Apr 25, 2008 8:20 AM

Former Member
0 Kudos

Further to Pavan's reply, make sure you setup old statistical data (extract old sales related data into your new infostr).

For any problems do revert

Thanks

Siddharth

Former Member
0 Kudos

Hi,

Thanks 4 all ur replies.

I chked in OMO1 its states its activated but it was changed from "Daily" basis to "Posting time" basis from clients side.

Now i think this is the reason he is not getting any data in the SIS & LIS.

So then how to fix this issue.

Thanks in adv.