on 04-24-2008 2:44 PM
Hi Experts,
In SRM 5.5 Server with R/3 4.7, when PO (service) is created with mupliple items (say 3 items), with multiple cost distributions (say 70% on WBS1 and 30% on WBS2). It creates the necessary commitments and fund allocation in R/3
Note:we are using SAP Funds management for budget creation and allocation, our budget are handled through funded program not through traditional FI budgeting.
when we do confirmation/Service entry, the commitments are reduced on first account assignment (WBS1). which leads to pending commitments even when the PO is closed the WBS2 project remains with few commitments.
is there is standard settings in r/3 that controls commitments? when our development team debugged it, there is no trace/hint where the issue occurs
Any help/hint will be greatly appreciated.
Cheers, Renga
Ramesh made a valid point. Refer this link
http://help.sap.com/erp2005_ehp_02/helpdata/en/ac/74a8374d4d6f5ee10000009b38f8cf/frameset.htm
Regards, IA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Renga,
Closing of the PO doesnt, make the commitment on the WBS to zero. Because you are allocating a amount to the WBS (either through FM or FI budgeting) which is used by the PO when you do a cost assignment. To release the funds remaining on the WBS the excess amount it needs to be released and the WBS element should be logically closed. I am not aware of the transaction with releases the excess funds in the WBS. But you can verify that.
Hope this helps.
Regards
Ramesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramesh,
i do agree with you, but what i mean by PO closing is by confirming and invoice.
Say if PO is confirmed fully and invoiced, which must reduce the commitment (if you have paid invoice to vendor, the amount you obligated/owe for vendor is done/complete) hence the commitment should be made to "ZERO". but in our case WBS1 commitment is reduced by 100% the other commitment (WBS2) remains the same. strange thing is adjustment of commitments automatically take place
I know work around to close the commitment in "SAP Funds Management". but my point is standard program should/must reduce it right?.
Cheers, Renga
Hi Renga,
If I understood the problem right :
You have a PO item with multiple account/cost assignment ie to WBS1 and WBS2, But when the PO is settled the whole amount is settled in WBS1 and WBS2 doesnt get any cost.
ideally this should automatically happen. its a standard process.
For me something looks fishy with the replication of the cost assignment in the PO while transfering to R3. Please check if the cost assignments are same in SRM and R3.
Regards,
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.