I have the following problem:

I want to send wmmbxy.wmmbid02 idocs over the XI to a customer. The order of the idocs is important because a cancellation must not be transferred before the goods receipt.

So I entered the queue processing in the partner profiles in my sap system. The problem now is that on the XI each of the idocs are given to a bpm. And this parallelism of the bpms mixes the order of the idocs so the customer sometimes gets a cancellation before the goods receipt. Is there a chance to handle this?

Regards.

Oliver.

Accepted Solutions (1)

Accepted Solutions (1)

prateek
Active Contributor
0 Kudos

What operations are u performing in BPM? If it is collecting idocs, then there is no way u can avoid this situation. Why dont u configure ur BPM to execute the steps sequentially

Regards,

Prateek

Former Member
0 Kudos

Well, thanks for the answers. I hoped that I didn't have to change the bpm because it is already in production. But it seems that I don't have any choice.

Other hints are still welcome.

Regards.

Oliver.

Answers (2)

Answers (2)

Former Member
0 Kudos

The solution is queue processing in the partner profile on the ERP system