on 04-24-2008 12:47 PM
Dear All,
We have defined a process like this.
We have a material A, in which will have B & C as other product (Co- product) . we will confirm material A only.
Now my requirement is i want to have inspection in production for the material B&C as individual lots
Kindly give your suggestions.
Selvam
Hi Selvam,
Assigned characteristics of Co Products in two different operations in the Hearder materials if you don't want to post the Co Products at the time of GR.
in this case system will create inspection lots against header material but you can inspect the co products as their operation descriptions.
hope this idea will solve your issue
thanking you
SADAN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Shouldn't be a problem. Set up inspection like you would for a finished product.
if you want the inspection, you must still do a GR for the co-product to place it in inventory and create the inspection lot.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Craig,
I dont want inspection for the finished materal (i.e for Material A ), i want the material B & C to be inspected. I have assigned inspection type as 03 in the material master and created different task list for each material. but when iam doing GR for the material B&C (co-product) inspection lot is not created.
But lot is created for the same material for the inspection type 04.
Kindly guide me which is best practice.
Selvam