Hi Friends,

We have a more than one inspection plan for a material with same usage

Suppose by mistake users have assigned wrong inspection plan then how can we change that assigned inspection plan and again assigned correct inspection plan.

we are using both inspection type 03 and 89

if anybody have some idea regarding this issues pl help me.

Thanks and regards

SADAN

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thank you very much to all of You

SADAN

Former Member
0 Kudos

Thank you very much to all of You

SADAN

Former Member
0 Kudos

Dear SADAN,

Happy yo know you problem is resolved. I is such that so you can reward points also!!!!!!!!!!!!!!!!!!!!1

Regards,

Shyamal

Former Member
0 Kudos

Hi

You have both inspection types 03 & 89.

Inspection type 03 , you need not worry , becauuse it is not by inspection plan & it is by routing.

Only in inspection type 89,, if it is not recordede the results, try in change mode to delete the assignment &reassign.

Regards

YMREDDY

Former Member
0 Kudos

Hi,

For I type 03 - In process insepction, it will read the routing not insepction plan, so there will be no worry.

For type 89 if you have to reassign teh correct T List then do....

1. QA02. Cancel the assign ment (Inspection Lot--> Function --> Withdraw Approval.

2. QAC3. Cancel the samples (If required as per your process design)

Then Go to QA02 again and assign the corect one.

Follow this process, it will surely HELP.

Best Of Luck

Regards,

Shyamal

Former Member
0 Kudos

Hi shyamal,

Is it possible if i do the inspection "with task list"

Thanks

SADAN

Former Member
0 Kudos

Hi Shyamal,

its working for Inspection Type "89"

Now i want to close this thread.

thank you very much