We have integration of cProjects 4.0 with R/3 4.6C. We are populating the cProjects work list into CATS. When user enter into CATS for first time it shows proper projects and user filling time against it and save.

When user entering into CATS second time it populate same project twice in work list.

Pl. let me know if there is any special settings.

Regards,

Karan Hon.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Karan ,

If there are duplicates, then it would be rather a program error than the customizing setting's issue. Does the problme occurs persistenly?

Please check if the report can give you some help.

https://www.sdn.sap.com/irj/sdn/wiki?path=/pages/viewpage.action&pageid=61926

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Zhenbo,

Thanks for your reply.

I was assuming the same that there may be some programmed error but finally i have got the error in Config.

In data entry profile i kept INPROCESS active which was giving me work list twice. Now same is been resolved.

Regards,

Karan hon.