on 04-24-2008 8:21 AM
hi all expert,
1)when user create sales order for BOM item.system show
message"Consider delivery unit 6 ZUN in item 000020"
where i can check the setting.
2)
user create one BOM with t code cs01.
mail item is-mm004
subitem is- MM02 and mm03
same sub- item is maintaind two time in one BOM
for example:
main item-mm04
sub-item------MM02 -
5 qty
MM02----
1 qty
MM03----
10 qty
MM03----
2 qty
in this case system is picking first Qty in our example
is 5 for mmo2 material and and for second material MM02
its taking 5 (not 1)
this is user issue what i should sugget to user
please tell me
as per my understanding they should not maintain same
material for two time with different Qty.they can maintain
material MM02- for qty 6(5+1)
please suggest me
regds
alicia
Dear Alica,
Why they are maintaining same material as two sub items then can maintain those as one sub item
So you ask them to maintain like this
MM02--6 qty
MM03--12 qty under MM04. Then try
I hope it will help you
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Alicia,
I believe this is only a warning message not an error, so you may be able to proceed. Otherwise edit the BOM by CS02 and remove the line with one quantiy and add it into the another to make it to six.
Prase
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.