Hi
Can you please inform me the how to get what are the changes which have happened on the WBS Element Master Data..... ( Just like we can get for vendor or Customer)
Regards
Ashwin
Small correction to your special feature "No change documents are written for settlement rules".
It's possible to active change documents for settlement rules by implementing BADi CO_SRULE_CDOC.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please find more details on Change document in Projects.
When does the system write change documents for changed field contents (not for a changed status) in the Project System?
o Project definition, WBS element, milestone for WBS element
- Indicator 'Change documents' is set in the project profile.
- The project definition and the WBS element have released a
status, for example, which allows change documents to be
written.
- For standard project definitions and standard WBS elements,
status 'released' must be set.
- Change documents are only written for those fields where the
'Change document' flag is set in the assigned data element.
o Network, network activity, relationship, production resource/tool
reservation and so on
- In the parameters for the network type, the 'Creation of change
documents' flag is set.
- Change documents are only written for those fields where the
'Change document' flag is set in the assigned data element.
Consider the following special features:
o No change documents are displayed for deleting or creating
objects.
o No change documents are written for the configuration of materials
in the network.
o No change documents are written for settlement rules.
o No change documents are written for changes within the service
specification outline within a service.
o If you create, change and then delete a WBS element during the
assembly processing with configuration, the change documents which
have been created until the deletion are no longer displayed for
the newly created WBS element.
Hope this will help you.
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try Tcode CN60. Ensure that 'Change Documents' check box is ticked in Project Profile (Tcode: OPSA). Note that there are 2 check boxes there, one to the right and other under Status Managemnet.
Hope this helps.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.