on 04-24-2008 12:10 AM
Hi all,
I have two tracks in NWDI. Track A (acting as source track) and Track B (acting as target track). I have defined a track connection of type transport between these tracks.
I approved a software component in track A, however the software component did not appear in the import queue of the target track B.
Any ideas?
Thanks,
Pradeep
Hi Pradeep,
What was the connection option you chose ?
I hope you have taken into account the various connection options:
Connection option
You can use the connection options to restrict the number of software components that are transported through a track connection. You can choose from one of the following options:
○ Transport All Software Components
This option is the default for all connections. All software components defined in the source track and target track are transported.
○ Transport Developed Software Components
When this option is set, only those software components are transported that are developed in the source track.
○ Transport Required Software Components
When this option is set, only those software components are transported that are configured as prerequisite software components in the source track.
○ Transport Selected Software Components
When this option is set, you can select your own list of software components to be transported.
Cheers,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
25 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.