In SAP APO, Please let me know where is the setting done for the resource to be constrained or unconstrained. Kinly send me a screen shot.

kind regards,

Abhik

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Your resource is responsible for production. Production capacity could be a constraint for SNP optimizer planning.

In optimizer profile you mention, 'production capacity' is a constraint (general constraints tab).

Satyajit

Former Member
0 Kudos

Hi,

Depends on the planning tool you are using and the type of resource used. You can use the PP/DS bucket capacity if you execute a bucket-oriented capacity check to find out whether sufficient capacity is available for an order in a certain period, such as a day or a shift. You can use the bucket-oriented capacity check in the CTP process and in block planning.

If you choose the setting From Time-Continuous Capacity, the system calculates the available capacity of the PP/DS bucket from the time-continuous capacity of the resource. You choose this setting if you use the resource for the CTP Process.

The available capacity of the PP/DS bucket vector is calculated according to the following formula:

Bucket Capacity of a Single-Activity Resource = Productive time of the resourse x Factor

Bucket Capacity of a Multi-Activity Resource = Productive time of the resource x Number of capacities x Factor

So a resource can be infinitely planned if the type is Multi-activity or Single-mixed. Also, you have options in the planning run where you can switch on 'Infinite Planning' if need be.

Regards

Vinod

former_member243834
Active Participant
0 Kudos

Are you talking about finite and infinite resource?