can any one tell me how to give MRP controller
while creating a material for MRP(material requirement
Planning) iwas asked to give 0001
if i give MRPcontroller = 0001 its not taking
pls help me to find me a solution for this!
Regards
Jino
Hi
Create the MRP controller with reference to your plant in customizing under MM->Consumption-Based Planning-> Master Data -> Define MRP Controllers
Every material that is relative to the planning run must be allocated an MRP controller number in the material master record.
With the MRP controller, the materials are assigned to a person or a group of persons who is/are responsible for monitoring material availability. By using the number entered here, it is possible, for example, to select the planning result per MRP controller. The MRP controller can either be one person or a group of persons.
Thanks & Regards
kk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.