Components checking problem

Hi,

I have an PP order of a header materials. for which the components are not see nin the stock requirement list. I have check the validity date of the BOM and all is ok.

Why is it so?

THe only thing is that the BOM was valid from 18.03.2008 and the SO for the header material was also created from 18.03.2008 and converted to PP order on the same day with backward scheduling finsih date as 28.03.2008 and start date as 20.03.2008.

Please guide what might be wrong.

Rg,

Vipul