Dear All,

I am using scheduling agreements with schedule line category CN & i.e I am not running MRP through scheduling agreement instead I am geenerating planned Independent requirements.

When I want to deliver the items in scheduling agreement all the items get copied in the delivery document.

I want only the confirmed quantities in the delivery.

Can any one help on this???

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member204513
Active Contributor
0 Kudos

Dear Wagela,

You try with the copy control settings

Go to VTLA transaction then select your document type then go in to the item level here you can find the copying routines (101 is the stndard routine) take the help from the ABAPer copy the standard one then you can make the changes according to your logic in VOFM transaction.

After developing the new copying routine assign that routine in VTLA transaction at item level instead of 101 routine.

I hope it will help you

Regards,