Hello Guys:
Currently I am on the "to be" definition phase on one of my projects and we have some questions about the sourcing functionality. We are not able to test it because our system is not configured yet, so I wonder if some of you have had some similar experience and could help us to answer this. when you have a contract in SRM and you use the renegotiate functionality after you create the new bid invitation and you accept the bid from your supplier, it is possible to update the original contract using as a reference this bid? I mean it is possible to load the new prices/items automatically to the same contract? or do we need to create a new one??
Hope you can help us out.
Hugo
Hi,
Some description is in help.sap.com.
[http://help.sap.com/saphelp_srm50/helpdata/en/f3/74d43ff9490d65e10000000a114b1d/frameset.htm|http://help.sap.com/saphelp_srm50/helpdata/en/f3/74d43ff9490d65e10000000a114b1d/frameset.htm]
Contract also has version management.
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the information guys, just one more thing when you update the original contract with this renegotiation functionality, the Items (with new prices or information) are updated automatically from the sourcing application to the original contract??
Thanks for all your information.
Hugo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.