Hi all,

I'd like to manage the SAP standar repair flow using project stock collecting costs and using project stock Q. Can I do this? Is there any "side effect"?

Thanks for Your help.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

We had tried this in our project and found it is not possible. You cannot assign stock type Q in the requirement class.