No Costing: cProjects 4.0 with 4.6C

Former Member
0 Kudos

Hi all,

We've done accounting integration of cProjects 4.0 with ERP 4.6C using Internal Orders.

We're unable to see anything in 'Costing' tab under Accounting. The warning message we get is :

'No Costing data exists'

Does cProjects 4.0 support this feature with 4.6C at the backend?

Please suggest.

Regards,

Vivek Pandey

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member201206
Active Contributor
0 Kudos

Hi Vivek,

Yes, the integration of cProj 4.0 with internal order is supported.

Beside the customizing settings mentioned above, please make sure, that there are costing relevant data are maintained in the cProject side, typically the working hours and rates, which are used for the calculation.

It is reommend to take a look at the Guides ( in the Q&A for cProject in Wiki), if any Plug-In has to be installed.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi

In this case make sure you have entries for Int Order type as $CPR

If it is not thr then may be you need to copy from base client.

Also make sure in PPOME you have done assignment to cost centers based on company code or controlling area.

Niranjan

Let me know if it helps !!!

former_member214272
Contributor
0 Kudos

Hi Vivek ,

You can do Single level controlling ( creation of internal order ) with cproject 4.00 and r/3 4.6c .

What setting you have made in R/3

IS Same as mention.

Create/Change controlling scenario for single-object controliing under cProjects:

Controlling Scenario: CPR1 Controlling Scenario for cProjects

Costing Variant: PCO2 Internal order

Costing Sheet: A00005 Standard/Order Type

Overhead key: SAP1 Overhead key 1

Results Analysis Key: 000001 Results Analysis (Int. Orders/Proj

Settlement profile: 20 Overhead costs

Strategy Seq.: SAPCRM CRM-CO Integration

Object Class: Profit Analysis

Functional Area: 0001 Functional area 0001

Under Define Controlling Scenario:

Project Type: *

Controlling Scenario: CPR1

Det. BAdI is not checked.

It must be same

Controlling Scenario: CPR1 Controlling Scenario for cProjects

Costing Variant: PCO2 Internal order

other setting as per you requirement.

and also check the error in T-CODE: COCPCPR

I am sending you the PPT go through that and check your setting.

thanks

sunil jawalkar