cancel
Showing results for 
Search instead for 
Did you mean: 

MC74 : how transfer SOP to PIR for a specific mrp area

Former Member
0 Kudos

Dear guru ,

i want to transfer Planning Data of a SOP Version for a single material to Demand Management.

The copy to Demand is run directly into the plant of the SOP Version.

I manage MRP Area.

How can I transfer directly SOP to PIR for a specific mrp area ?

Thanks in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi..

In MC87 you have to first create planning data.. SOP.

Then if you go to MC74 your planning data will be transferred..

Ii.e you will get the PIRs automatically from Demand management..

Hope the above clarifies..

karthick