Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Selection of scheduling scenarios

Hi,

While scheduling my project using bottom up approach, the system defaults the method for plan method/ basic and plan method/fsct as "Bottom up (taking dates of higher level WBS into account).

Is there a way i can change this to "strict bottom up" as I need the system to adjust the dates of the WBS during scheduling (including reducing the duration)

thanks

Anand

Former Member
Former Member replied

In project profile Trnsaction code OPSA

In Plannin board board/dates tab

WBS time schedulling

Tick on with activities

In Planning method

put below values

Plan.meth/basic 4

Plan.meth/fcst 4

Calc. with act. 1

This profile will do the scedulling by Bottom up method only

Rgds

0 View this answer in context

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question