Need to enter order type at the time of order creation through MD04

Former Member
0 Kudos

Hi,

we need to enter order type when creating process order through MD04.

In our scenario system pick up default order type PI01 where as there is not order type assigned in scheduling profile which is assigned to the material.

pl give some clues

thanks and regards

SADAN

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi thirajan,

as we already mentioned there is not order type is assigned in scheduling parameters.

pl give the right answer

regards

SADAN

Former Member
0 Kudos

Sadan,

Check out Transaction Code: OPPE "Define Order Type for Conversion to Production/Process Order"

Here you define the order type that is automatically set when converting planned orders into production orders or process orders.

Seems for the plant where you are trying to convert planned order to process order, order type is not set. Hence when you try to convert the same through MD04 you have to give order type everytime to convert to production order.

Regards,

Kiran

Edited by: Kiran Magar on Apr 30, 2008 11:17 AM

former_member187991
Active Contributor
0 Kudos

hi

check in T code CORY for your plant there will be scheduling profile where you have assigned the default order type

regards

thyagarajan