Pls. explain what is “Split number” and the “Capacity ID” 10000426

Former Member
0 Kudos

When I switching the network activity to TECO, the system throws an error “There are CATS records for the object to be deleted”. However we have transferred all the CATS records, but in CATSDB table found “Split number” as 1 and there is “Capacity ID” 10000426.

Can anyone explain what is “Split number” and how to check the created “Capacity ID” 10000426

Thanks in advance.

Regards,

Harisha

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

Hi

A "split" is a resource assigned to your network activity

You are assigning 1 or more individuals to perform that activity

In CJ20N view the splits using the Personnel Tab of the Network Activity

Each person assigned to undertake that Activity is a split

So the first person assigned will be split 1 and the second split 2 and so on

If I remember correctly the Capacity ID is the internal no of the Person you have assigned to that Split (but I may be mistaken and it moght be the actual HR Mini Master No)

With regards to your particular issue OSS note 894300 may help

Hope this helps

Steve

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Harisha,

If you are interested, the constuling note 543362 can give you more detailed information at this area.

Kind regards,

Zhenbo