Hi Folks,

Actully im a technical consultant. Now I want to study Projrct systems.

tell me the process flow of the Project systems. And also I need important transactions and Master tables.

Please anybody guide me.

Thanks for your valuable time,

Points will be appreciated.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member633158
Participant
0 Kudos

Dear Jasmine

How are you getting on with Sanjay's Instructions and help.

I am also in the same situation where you are.

I am a FICO Consultant but need to setup the Projects for my client.

I appreciate if you can share the information which helps me as well.

Former Member
0 Kudos

Project Systems:

1. Project Structure Creation

Creation of Project Definition, WBS Element, Network, Activity(Internal, External, Cost, Service) (Tcode: cj20n)

2. Planning:(Tcode: cj20n)

Date Plannnig

Material Planning

Service Planning

3. Execution (Tcode: cj20n)

Change Project Status / Project Release

(status change CRTD-REL)

Confirm Activities (status change REL-CNF)

4. Reports:

Progress: cne5

Plan/Act/Variance s_alr_87013432, s_alr_87013542

5. Project Closing

Settlement (Tcode: cjb2, cj88)

Close Project (status change CNF-TECO-CLSD) (Tcode: cj20n)

75% of work is completed in cj20n - Project Builder

Main Tables:

PROJ, PRPS, AFCV, etc...

Happy Learning

SSanjay

former_member633158
Participant
0 Kudos

Dear Sanjay

Thax. for the info.

I am also in the same position at the moment.