on 04-21-2008 8:48 AM
Hi Folks,
Actully im a technical consultant. Now I want to study Projrct systems.
tell me the process flow of the Project systems. And also I need important transactions and Master tables.
Please anybody guide me.
Thanks for your valuable time,
Points will be appreciated.
Dear Jasmine
How are you getting on with Sanjay's Instructions and help.
I am also in the same situation where you are.
I am a FICO Consultant but need to setup the Projects for my client.
I appreciate if you can share the information which helps me as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Project Systems:
1. Project Structure Creation
Creation of Project Definition, WBS Element, Network, Activity(Internal, External, Cost, Service) (Tcode: cj20n)
2. Planning:(Tcode: cj20n)
Date Plannnig
Material Planning
Service Planning
3. Execution (Tcode: cj20n)
Change Project Status / Project Release
(status change CRTD-REL)
Confirm Activities (status change REL-CNF)
4. Reports:
Progress: cne5
Plan/Act/Variance s_alr_87013432, s_alr_87013542
5. Project Closing
Settlement (Tcode: cjb2, cj88)
Close Project (status change CNF-TECO-CLSD) (Tcode: cj20n)
75% of work is completed in cj20n - Project Builder
Main Tables:
PROJ, PRPS, AFCV, etc...
Happy Learning
SSanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.