Production order start date in past

Former Member
0 Kudos

HI Experts.

Is it possible to create the production order start date in the past, If so pls explain me.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Yes.. it possible.. Kindly refer below SAP Help link:

Scheduling Types - Production Orders (PP-SFC) - SAP Library

Former Member
0 Kudos

Hi Kumar

It is definitely possible.

Do setting in Plant parameter. T code OPPQ, there make a tick mark in the order start in the past allowed. For MRP group OPPR.

Also you have to specify the number of days allowed in the past in Scheduling parameter of plan order OPU5 at the bottom. And for production order scheduling parameter OPU3.

Hope this is clear

Regards

J . Saravan