HI Experts.
Is it possible to create the production order start date in the past, If so pls explain me.
Yes.. it possible.. Kindly refer below SAP Help link:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar
It is definitely possible.
Do setting in Plant parameter. T code OPPQ, there make a tick mark in the order start in the past allowed. For MRP group OPPR.
Also you have to specify the number of days allowed in the past in Scheduling parameter of plan order OPU5 at the bottom. And for production order scheduling parameter OPU3.
Hope this is clear
Regards
J . Saravan
Edited by: J. Saravanan on Apr 21, 2008 5:09 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.