We have set a availability planning for all our JMS channels.

Here all the JMS channels should stop at 7.45pm till 8.30pm.

From past 3 days, the availability planning seems to be executing twice.

At 7.45pm there are 2 entries of "stopped" and 2 entries of "started" at 8.30pm in

the CC monitoring->administration information".

Since we have 2 server nodes running, this is causing an error on the one of the server nodes.

Request you to please come up with the suggestions as the solution to this issue is vry urgent.

Thanks and Regards,

Raghu

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

redefined the plan with exactly the same setting and is working fine! Bug in SAP probably??

vijay_b4
Active Contributor
0 Kudos

Hi,

Inactivate the adapter status for any one of the servers.. so that it wont occur twice..

Regards,

Vani.

Former Member
0 Kudos

Hi Vani,

Thanks for the reply.

we need the adapter running on both the server nodes.

It always used to run only once since an year. but suddenly it is acting as explained above.

it used stop once and start once on the scheduled time on both the nodes. but it does it twice from past 3 days.