on 04-18-2008 9:43 AM
Hi,
I have executed OLI7 in order to update a Sales Order into info structure S999. After I have used SE16 to check the data updated, I found that all of the materials in the Sales Order are having the same "Current Date"(Period to Analyze), except 1 material which is having the different date.
eg.
Date Material
==== =======
07.03.2008 101243
07.03.2008 101244
07.03.2008 101245
11.03.2008 101246 <-- error
For material 101246, its Material Statistic Group in MM has actually been modified to "1" from blank before executing OLI7 as this material has not been updated into any info structure properly before this.
Can anyone advice what will be the cause for this?
Thank you.
Regards,
Ken
Hi
Have u tried using MCSY first before you use OLI7 after updating material stat group.
I think u can still try first with Reorgnization using MCSY and then check Regenerate infostructure and that may give you desire results.
Hope this helps
Regards
Mandar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
A little more information for this problem.
When I used VA05 to display the respective sales order, the document date for material 101246 is 07.03.2008 as the rest. I am still stuck with this problem...
Hope to hear some suggestion from gurus out there..
Thanks~
Regards,
Ken
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.