on 04-18-2008 7:08 AM
hi,
Asset Po raised for 5 nos and assigned 5 Assets in PO. Later Vendor supplied 3 assets, GRIR taken. While doing MIRO. System is posting the three asset value to 5 Assets. IT is not taking 3 assets.
After 2 assets were delivered by Vendor, GRIR taken. While doing MIRO system is posting 2 assets value into 5 assets. If we check the AWO1n for the particular one asset, system is showing two purchase value. This i don't want.
First system want to post 3 asset value to 3 assets and 2 assets value to 2 assets. How can i achieve this? Please give your suggestions.
govind.
Hi Govind,
When you have 5 assets you have to create 5 line items in your PO and not create one PO line with 5 asset numbers.
When you do did the system split the costs over the assets.
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In this case you can the option what now is going wrong but make then 1 posting on your PO.
An other way is to post these amount on a temp account and use ABZON with Multiple asset to make the posting on the asset.
When you have the asset number and the values in a excel file you can copy it as block's in the transaction
Paul
Hi,
We can define the partial goods receipt for POs and can also define for shipment to various places based on the order types.
Thanks and regards,
Ravi Vruddhula
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.