on 04-17-2008 5:37 PM
Hi
To display Planned Independent requirements in transaction MD63, I have to enter one material at a time.
Is there any report where I can enter multiple materials at the same time to see their Planned
independent requirements in a single report/screen?
I do not want to use Product Group.
Sincerely,
Ketan
Ketan
You can use Requirements Plan number. Enter a plan number here and then proceed. You will be abl to enter for different materials and also view them in a single screen.
regards
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi KETAN,
Requirement paln no. is key Key which can be given to create and to identify one or more planned independent requirements.
Go to md61, click the radio button for req plan number. Give some number say as 100 and press enter and then continue.
Coma back in case of problem.
Regards,
Satyajit
Hi,
1. Go to Transaction code MD79
2. Give the Following details
Plant
Version : The respective PIR version
Requirement date:
3. This will allow you to select all the PIR in the respective plant and as per the selection condition
4.Then hit the execute button
5.You will get a pop up as
EXPORT LIST OBJECT TO XXL
6.And in this by can selec the TABLE
7.Then You get a Popup for Microsoft excel
Now save this sheet ...this will display you the the PIR in the whole plant
This is the only standard report available...for the PIR display..
Kindly let us know if this information was useful and solved your problem..
Reg
Dsk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.