Hi.

My BPM must send thousands of IDOCS to SAP.

I've made a test sending 400 vendor IDOC to SAP and spent more than 6 minutes on it.

It's a long time?

In the future, i will have to send more than 20.000 FI IDOCS. What's the fastest way to send them?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Inigo,

Are you using IDoc packaging or sending idocs one by one ?

If you package and send a IDocs then the performance will be better.

Check if this helps..

Anand

Message was edited by: Anand Torgal

inigo_sacramento
Participant
0 Kudos

i'm sending 1 by 1.

I have a XML file and i make the mapping 1:unbounded

Then with a block in the BPM i send one by one y parforeach.

How can i package and send the idocs in order to get better performance?

Thanks.

Former Member
0 Kudos

Did you check this..

Anand

MichalKrawczyk
Active Contributor
0 Kudos

Hi,

remember you can only use packages with >= SP11

have a look at note: 778890

IDoc Adapter: Outbound packaging for IDocs

Regards,

michal