Hi.I have a doubt on "On what basis the system chooses the MRP Element which is proposed for 'reschedule in' whenever there is sudden requirement.
Rescheduling Horizon:
It is defined in Plant parameter tcode OPPQ. For rescheduling check use tcode OMDW.
In rescheduling check system will consider firmed elements ie, Firmed planned orders, Production order, Firm purchase req, QM ins lot.
For easy understanding we can assume having firmed planned order qty 10 nos on 29.04.2008.
Sales order qty 10 nos date on 20.04.2008.
Rescheduling horizon say 20 days.
When mrp run system do net requirement calculation ie, Plant stock + Firmed receipts issues safety stock = Available stock.
If you mention 100 days in horizon system will consider the firmed planned order on 29.04.2008. System wont create any procurement proposal.
And system proposes to reschedule the firmed planned order to 20.04.2008
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Darma,
thanks a lot for the reply.My doubt is as you mentioned
there is a requirement for 10 items on 20.04.2008
and there are three firmed receipts 2 on 29.04.2008 each for 9 units and one on 30.04.2008 for 10 units.Now which MRP element will be considered for rescheduling proposal.
please advice.
Hi,
Rescheduling horizon defines the period for bringing the receipts that should be
taken into account for rescheduling.
There are two process
1.Reschedule in - Bringing the process forward Exception message 10
1. Within the recheduling horizon the system checks whether after the
requirement a firmend receipts exists which can be used to cover this
requirement.
2. Then the system displays the message Bring the process forward and
exception message 10
3. The net requirement calculation uses the receipt and the system will create
new procurement proposal only if there is any shortage.
4. For this we need to define a tolerance value for bringing the process in
tcode OPPQ /OPPR
The system checks compares this value with the difference between order
finish date- Reqmts date.If this difference is more than the tolerance value
the system issues the message for the MRP element to bring the process
forward if the reqmts date lies before the firmed receipt element date.
5. Same process for Postponing the process Exception message 15.
During MRP the system carries out Rescheduling check automatically. No Tcode is reqd.
Rescheduling check is to change the dates of already existing firmed receipts
which were not planned on the same day as the requirements day to suit the
requirement.
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.