on 04-16-2008 1:08 PM
I have created a material for which the availability was 01
i created a sales order using this materaial.
Now I went to MM02 and changed the avaiablity to 02
Then in va02 in availability check i could not see the cnaged 02, but it is freezed where i cannot change the 01 to 02
Please guide me how to change it...can it happen or we again need to create new sales order???
Dear Viswanath,
You need to create new sales order to get the material master changes in the sales order.
Because when you were created that order Material master having the data is different i,e 01,
Why you the system is not allowing you to change availibility check at sales order?
Availability check 01 or 02 will come to sales order from material master only we can,t change that in sales order.
I hope it will help you
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.