Hi,

We need to generate inspection lots when there is a inbound delivery done.The neccessary setting's has been done and insp lot is getting created.But when we do PGR within Inbound delivery we get a error as ''Status of inspection lot 600000000000 / partial lot 000000 does not allow good issue''.We need to do PGR and then process the lot.

Appreciate your help in this regard.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

former_member698542
Active Contributor
0 Kudos

Hi Shanawaz,

Please process the inspection lot and make Usage Decision, then you will be able to do PGR.

Tcodes: QA32 - Inspection lot selection

QE51N - Results Recording

QA11 - Usage Decision

Thanks and regards

muruegsan

Answers (3)

Answers (3)

mshaan_blr
Explorer
0 Kudos

Hi,

We need to repair the product returned, by inspecting it and we need to do after the PGR has been done.The simple scenario is we can de- activate the insp lot creation in the material master so that no insp lot is created during inbound and after we do PGR ,how do we create the inps lot ?.No manual creation of insp lot in this case.

Thanks

Former Member
0 Kudos

Shahnawaz,

Here u will have to use insp type 05 instead of 06 in material master.And second thing assign movement type 655 to schedule line category u r using (may be DN if using std).

It will solve ur purpose.

former_member42744
Active Contributor
0 Kudos

SAP uses service notifications for tracking and performing repairs. It is standard functionality. Receipting of the material is done via the notification as well as the creation of the inspection lot.

You should review the help files on this process.

Craig

mshaan_blr
Explorer
0 Kudos

Hi Guys,

You are right we can do PGR if we process the inspection lot thru UD and then do PGR.What i need to know is that can we create a Insp Lot during Inbound and process it later after we do PGR.In other words we need to do PGR and them process the inspection lot.

Thanks

Former Member
0 Kudos

Hi

In Std SAP for any posting inspection lot is created , we can not process that without processing the inspection lot.

Your requirement will not be met by Std SAP.

Can you explain your scenario a bit detail,as to why require like that.

Regards

YMREDDY

Former Member
0 Kudos

Hi

It looks that you have not processed the inspection lot.

Pl. process the inspection lot like record the results & carryout UD.

Then you will be able to post it.

Regards