Hi QM gurus,
When ever the material comes inside, GR is done and inspection lot is generated.
My scenario is when results are recorded for the inspection lot,for specific characteristics when they record results say for 5 samples,if they are not satisfied with the results they go for another 5 sample Nos(Resample) and record the results.
How to map this scenario in SAP.
Regards
Mohan
Hi,
you can dynamic modification rule . Create a dymanic modification rule as per ur requirement and assign it in the quality plan of matrial .
Amol