on 04-15-2008 7:05 PM
Hi All,
We are using ECS for plan driven procurement and bidding engine in our system.presently we have configured the system in sand box.We can able to do the entire cycle like PR transfer from R/3 to Sourcing cockpit upto PO creation in SRM.But PO's are not replicating to R/3. can any body suggest what may the problem for PO replication to R/3.
Thanks in advance.
Nanaji
You need to check mainly the backend integration settings
like "Define backned settings" with correct sys type & RFC destn.
required attributes pertaining to backend in SRM org
check logs in SLG1 & RZ20 in SRM
BR
Dinesh