on 04-15-2008 10:06 AM
Hi Experts.
Hope you can help me.
I am trying to find the planned data for wbs element in datasource 0CO_OM_WBS_2, but the source gives 0 rows.
I know there are some wbs elements lines that are planned for in transaction CJR2 ( Planning of cost on WBS element ) on the R/3 side.
Please help me to find the correct Business Content source for these numbers .
Or tell me if there are some things that need to be done on the R/3 side.
Ingrid
Hi Ingrid,
0CO_OM_WBS_1 contains both plan, actual and commitment so might be usefull to you.
Hope it helps.
BR
Stefan