on 04-15-2008 8:54 AM
Hi Guys,
Our Trans filesystem got full yesterday so many transports stuck at export stage. these are virtually doing nothing, we ask user to create new transports for all the changes and release them again.
But we want to delete all those stuck transports, because otherwise we need to answer for weekly transports. Please advise how can we delete them or atlease if we can remove the project assignment from those transports?
Thanks in advance,
Mad
Reason mentioned above
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you check the status in the import monitior? tp log? Job monitor?
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for reply,
Yes we did! Actually we have one background job schduled to acutomatically import all the released transport every half an hour! so those were also stuck so we'd to kill all the jobs and infact all tp sessions at unix level so these are not doing anything from past 24 hours! now new transports are moving but those are stuck, waiting for something
Now we want to delete them, one Idea I got right now, If we delete all the entries for those transports from E07* tables.
Now I want to know, are there any more tables other than E07* tables which contain transport info... we'll clear all the ALOG and SLOGs for those transports.
any IDEAs?
Thanks
Hello Madhusudhan,
Don't tamper with E07* tables for such trivial reasons.
Secondly you mentioned that the transports are struck somewhere? But where exactly. Are they showing up in STMS import queue?
If so then please select them and delete them from the import queue. What is the issue with that ?
With Regards.
Ruchit.
Hello Madhusudhan,
In one of your old posts you said "Nothing in import queue those are waste transports now" ...and now you say "Well we have weekly transports happening to prod and we don't want these transports to appear in that list!
"..
Which list are we talking about here ?
Regards.
Ruchit.
We do create Project every week so If someone create some transport it get added to that project and on weekend we do project "import all" so even if we delete them from the import queue, project assignment will be there with those transports. and over weekend those will appear.
Anyway I better close this topic here! because I am not getting any productive answer! Thanks for all your afforts
Hello madhusudhan,
We also do the same in our project and I think probably you thinking is basically flawed on these lines. There is no direct way of importing a project as an entity. In the end you only import transports attached to a project. I mean unless the transport is in import queue it will not show up there just because you are importing projects! And let me tell if we import upto 15 projects in a single go.
The transport has to be in buffer to get imported and not in some project .
Regards.
Ruchit.
User | Count |
---|---|