on 04-14-2008 5:25 PM
Hi,
I changed in VOV6 the movement type for my schedule line
to 502.Now I get message nr M7 226-The configuration of movement class with error.
Impossible to make PGI with movement type 502.
Where I should configure more ?
Thanks in Advance and regards
Guilhermo
what was the movement type before you changed it to 502.
Check transaction OMJJ to compare movement type 502 & the one you changed. do they have same allowed transactions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Luis,
In SD normally, the movement types starts from 600.
I am not sure under what scenario, you have entered 502, which RE receipt without PO.
For SD PGI, you need enter movement type 601.
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.