Hi,

whether there is a possibility in some way of distinguishing planed orders made by MRP depending on element MRP which they came into existence for.

For example: planed order nr 23456 is for U1( Release order for a stock transfer order, Ord.DS ),

planed order nr 23457 is for SH (Safety stock, SafeSt ).

Artur

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Its the Order type of the planned order , that does this role.

For ex.

MRP Element Order Type Description

xxxxx/Ord. KD Make to Order

xxxxx/IndR VP Independent Requirements

xxxxx/Extp NB external procurement

Hope its clear.

Regards,

Sheik

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear,

If it is a MTO scenarion, then you have a link of sales order or project link whicg you can see that in MD04 withn seperate segment,

if MTS scenarion then in MD04 you can see the pegging requirement so that system will show the requirement for which the planned order receipt is created.

Double click on planned order and click on peggging requirement...system will show the STO or sales order.

former_member566378
Participant
0 Kudos

Sorry, I asked this question imprecisely. I work in MTO scenarion. I need to find (ex. in COOIS or SAP Query) planned orders generatated from U1 type requirement (Release order for a stock transfer order).

Artur

Former Member
0 Kudos

Hi,

Please check with table PLAF

Pradeep