Costs on a Work Order - Tables

Former Member
0 Kudos

Hi,

In a maintenance work order there exists three costs

(1)Estimated Cost

(2)Plan(ed) Cost

(3)Actual Cost

Further more the costs may be (1)internal labor cost (2)material cost etc....

The estimated cost is stored in the table AUFK.

In which tables are the Plan & Actual costs stored.

I have available with me tables AVFC and AUFM that show costs..but I do not know which figure belongs to which category.

Thanks,

KF

Accepted Solutions (1)

Accepted Solutions (1)

former_member192718
Active Contributor
0 Kudos

Estimated cost Table : PMCO3

Planned and Actual Cost : PMCO

Other tables for the help is PMCO2, PMCO1

Regards,

Kaushal Rai

Edited by: Kaushal Rai on Apr 16, 2008 11:42 AM

Answers (2)

Answers (2)

paul_meehan
Employee
Employee
0 Kudos

Hi,

Table PMCO should give you the cost information by value category per order.

Value Type will identify if actual cost or planned costs - see F4-Help on this field for values.

-Paul

peter_atkin
Active Contributor
0 Kudos