on 04-11-2008 9:54 AM
Dear cons
when we use t-CODE CJCO for one project to next year the system transfered all the budget( more than one project) . how can we reverse it.
nrk
Hi
As far as I know there is no SAP Standard way to reverse CJCO automatically
You will probably have to manually undertake the steps to change the Bugdet values
Was the values for all Projects done in error or did all Projects run even though only 1 project was entered in the selection parameters
If the latter, I suggest you go back to SAP
If the former, chop the hands off of the person who ran it
Steve